![]() | Provision of Housing to Government Employees, and Post Project Appraisal Procedures for Capital Works Projects |
the quantity of surplus houses throughout the public
sector;
the need for public sector organisations to identify
the extent of housing not required in order to facilitate the rationalisation of housing stock; and
the need for improvement in the standard of inventory
records and management information systems.The report also addressed works contract procedures and concentrated on an assessment of the pre-construction and construction stages of the project management cycle. It included an examination of various capital works projects undertaken within the Victorian public sector. Key audit findings were:
formal post-project review systems and procedures had
not been developed;
excessive delays between the date of construction completion
and the date of final payment for works contracts were excessive;
procedures to evaluate the performance of project
managers were inadequate; and
prescribed departmental procedures for the assessment
of consultants' and contractors' performance were generally not followed.Price: Out of print. Photocopies are available at $10.00 per copy.